IGG Exonerates Works PS Bageya, Orders Interdiction Of Engineer Over Busega-Mpigi Cost Explosion

IGG Exonerates Works PS Bageya, Orders Interdiction Of Engineer Over Busega-Mpigi Cost Explosion

By Spy Uganda

The Inspectorate of Government has cleared Ministry of Works and Transport Permanent Secretary Waiswa Bageya of wrongdoing in the controversial cost escalation of the Busega-Mpigi Expressway, shifting the spotlight to decisions made under the former Uganda National Roads Authority (UNRA).

In a statement dated October 23, 2026, Inspector General of Government Lady Justice Naluzze Aisha Batala said investigations had established that Bageya was not involved in the earlier decisions that triggered the project’s soaring costs.

The IGG has consequently directed Head of Public Service and Secretary to Cabinet Ruth Nakyobe Mbonye to allow Bageya to resume his duties, while ordering him to immediately interdict Engineer Isaac Wani, the Commissioner for National Roads, to facilitate further investigations into his alleged role in the project.

Wani previously served as Director of Network Planning and Engineering at UNRA when key decisions linked to the cost escalation were made. His interdiction is an administrative measure to facilitate investigations and does not amount to a finding of guilt.

Bageya has also been instructed to make interim arrangements to ensure continuity in the commissioner’s responsibilities during the interdiction.

The decision marks a significant development in the scrutiny of one of Uganda’s most expensive road infrastructure projects, whose estimated cost has climbed from an initial contract value of Shs547.5 billion to figures approaching Shs2 trillion when associated works are included.

According to the Auditor General, UNRA signed the construction contract on June 18, 2019, before detailed engineering designs and reliable cost estimates had been adequately completed. By March 2023, the estimated project cost had risen to Shs1.35 trillion, with inadequate design preparation identified as a major factor.

Works and Transport Minister Fred Byamukama has since indicated that the expressway itself is estimated to cost about Shs1.3 trillion, while a proposed Busega Systems Interchange could require an additional Shs700 billion.

The Ministry of Works and Transport has attributed the increases to design and scope changes, including realignment, additional interchanges and other infrastructure requirements. However, questions have persisted over whether the changes were justified, properly authorised and offered value for money.

The IGG’s inquiry has examined the circumstances surrounding the redesign, including allegations that sections of the road were redirected through swampy terrain, potentially increasing engineering costs and compensation claims. In July 2026, investigators conducted an on-site inspection as part of efforts to establish how the estimated cost rose from roughly Shs600 billion to Shs1.3 trillion.

The financial and implementation challenges have also affected the project’s delivery schedule. An Auditor General’s report for the financial year ended June 2024 indicated that funds allocated for civil works had been exhausted by May that year, when physical progress stood at 40.86 per cent. Certified works worth Shs30.8 billion remained unpaid at the close of the financial year.

Construction later stalled before resuming in 2026 following additional financing approved by Parliament in October 2025, including approximately Shs781 billion from the African Development Bank and Shs117 billion from the African Development Fund.

By June 2026, physical progress had reached 47.15 per cent, with completion now projected for December 2028, subject to funding and other implementation challenges.

The 23.7-kilometre four-lane expressway is intended to ease congestion along the Kampala-Masaka corridor and improve connectivity between the capital and western Uganda. Its prolonged delays and escalating costs have, however, placed project preparation, design management and public expenditure under sustained scrutiny.

With Bageya cleared of involvement in the earlier decisions, the latest IGG directives place renewed emphasis on establishing individual responsibility for the choices that drove the project’s cost escalation. Investigations into the alleged irregularities remain ongoing.